Roads & mobilityThe city has a 2025–2029 staged water, sewer, roadway, duct-bank and stormwater reconstruction timeline; the earlier utility phase was scheduled October 2025–May 2026, and the next phase June 2026–December 2027.
Water & utilitiesCity project schedule reports March 2024 construction start and December 2026 scheduled completion of an underground stormwater treatment system and constructed wetland; actual closeout is not confirmed.
Future projects
10 projects
Planned or in design or procurement; construction not yet confirmed.
Water & utilitiesDesign of a regional stormwater quality and flooding treatment facility is underway and expected to be completed in December 2026; construction start is not independently confirmed.
Water & utilitiesCity plans procurement of a design-build team in 2026 and selection in second quarter 2027 for a master flood-protection programme exceeding 600 acres.
Roads & mobilityPart of the five-project Eastern Shore Drive flood protection bundle; vulnerable portions of Lynnhaven Drive will be raised to reduce flooding.
Water & utilitiesThe Eastern Shore Drive Bundle lists a new pumping station at Lynnhaven Colony Park; bundle has forecast 2026–2029 delivery, not separately verified station mobilisation.
Water & utilitiesCity includes a pump station and automated tidal gate near Lynnhaven Drive and West Great Neck Road within the Eastern Shore Drive Bundle.
Water & utilitiesCity's Eastern Shore Drive flood protection bundle includes canal widening and deepening to improve conveyance and reduce backup during storms.
Water & utilitiesThe Eastern Shore Drive Bundle names upgraded street drainage infrastructure on Cape Henry Drive; full bundle cost is $73.5 million, not a separately assigned allocation.
Public facilitiesThe Office of Public Facilities lists its Beach Maintenance Facility among managed CIP public-facility projects; individual construction or completion phase is not supplied.
Public facilitiesThe city maintains Fire Training Center Improvements IV as an individually named public-facility capital programme.
Public facilitiesPublic Facilities maintains a dedicated Virginia Aquarium Renewal and Replacement III project, distinct from its building systems work.