Implement targeted crossing signal changes and later Caltrans turn protection subject to traffic-model review.
13–14 April 2026 city–Caltrans design meetings: City and Caltrans discussed exclusive pedestrian signal phases and protected left-turn options; modeling review remained open.
Shorten crossings by more than half, introduce pedestrian beacons and future ADA-curb upgrades; actual installation confirmation outstanding.
2026 municipal safety-design programme: City sets out RRFBs, paint-and-post crossing reduction, lighting and later concrete curb extensions as distinct work stages.
Design protected turn signals, visibility and crossing changes, new curb ramps and sidewalk repairs.
2026 city Local Roadway Safety Plan priority list: City classifies this as design-stage Tier 1 intersection safety work ranked seventh in the city's priority study.
Improve multimodal travel and bicycle connectivity, signals and roadway operations; park-and-ride mobility hub is not part of current scope.
April 2026 city detailed-design meetings: City held April 2026 public meetings showing refined engineering options and confirmed the separate mobility hub is excluded.
Identify railway crossing upgrades to improve vehicle, pedestrian and cycling safety before any train-horn quiet-zone designation.
2026 city transportation capital programme: City lists quiet-zone rail crossing safety design; no Federal Railroad Administration establishment or final delivery confirmed.
Replace the structurally aging bridge while retaining a crossing for vehicles and pedestrians, coordinating utilities and pile installation.
April 2026 Phase 1 construction window: City scheduled bridge replacement in two stages, with west-side works April–October 2026 and east-side works April 2027–July 2028.
Replace play equipment and associated park paths and amenities; the city's 18–24-month duration is an estimate, not a completion certificate.
2 June 2025 construction commencement: City confirms the park renovation contract was awarded 17 March 2025 and physical construction began 2 June 2025.
Build protected bicycle lanes from Bermuda to 28th and a bike boulevard southward, plus crossings, refuge island and signal changes.
April 2026 site progress report: City reports completed curb-ramp and median works in spring, with paving, signals and protected bicycle lanes scheduled as a later phase.
Public, original-source-backed development and capital improvement projects in San Mateo, California, separated by current, future and completed status. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.