Latest documented evidence Selected dated project-owner milestones; this is not a live feed or confirmation that work happened today.
Find current projects Search 9 curated current project records, or open the historical archive .
Search project or location Project typeAll types Public facilities Planning & development Industry Roads & mobility
9 current projects
No projects match those filters.
Upcoming and preconstruction 5 selected projects
Planned, reviewed, approved or tendered. Forecast dates are not evidence that construction started.
Planning & development · $3m federal support announced; design and start unverified Next residential phase of the long-running Arrowhead Grove redevelopment, separately financed from Alder Square.
24 April 2026: Housing Authority and Congressman Aguilar announced $3m in FY2026 community-project funding for a future affordable-housing phase.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · County conditionally committed $28m Proposed mixed affordable, workforce and student housing near college facilities, led by the community college district.
20 October 2026: Supervisors supported a college-district housing concept with a conditional $28m funding commitment.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Industry · Preferred developer selected; exclusive talks Proposed transformation of long-vacant Arden Guthrie land into retail and dining with related infrastructure.
19 August 2026: City Council selected Panorama Development as preferred development team for a 17.61-acre city-owned commercial site.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Federal grant secured; construction not verified Proposed renovation of the Nicholson Park community center following delivery of the outdoor park reconstruction.
15 August 2026: Following the park reopening, City said it secured $850,000 federal support for a separate community-centre refurbishment phase.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Planned second installation package Follow-on solar road lighting installation, distinct from the completed 397-light programme.
26 August 2026: City identified 83 additional solar streetlights planned across five street corridors following installation of 397 lights.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Documented construction 4 selected projects
Works that project owners identify as under construction; not a live on-site report.
Planning & development · Construction underway; delivery forecast 2027 Alder Square is the 92-unit fourth redevelopment phase replacing former Waterman Gardens public housing.
4 November 2025: Housing Authority and National CORE broke ground on 92 new affordable apartments in the fourth phase of Arrowhead Grove redevelopment.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Groundbreaking held January 2026 Combined educational/recreation facility with building renovation and outdoor space for sports and community activities.
27 January 2026: City Housing Division confirmed groundbreaking for El Sol Park & Learning Center.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · Groundbreaking held 25 March 2026; construction underway A thirty-home affordable supportive housing community on E Street for low-income and formerly homeless veterans, with wraparound services and a 2027 opening forecast.
25 March 2026: U.S.VETS, Kingdom Development and City and County officials broke ground for thirty permanent supportive homes for veterans and their families.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Late-August construction start; completion unverified Approximately three-quarter-mile downtown road pavement rehabilitation and signal loop restoration.
31 August 2026: City scheduled grinding, repaving, striping and traffic-loop reinstatement to start on 31 August.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Twelve deeply sourced housing, infrastructure and public-space projects in San Bernardino. Agency publications and dates distinguish reported works, awarded funding, forecasts and completed openings. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.