Resurface approximately 12,600 linear feet, replace 34 access ramps and 2,500 square feet of sidewalk; verify executed contract before asserting construction commencement.
25 August 2026 council construction award agenda: City Council agenda recommended Hardy & Harper construction contract for $1.434 million after the project reached final design.
Resurface approximately 16,500 linear feet, replace 42 ramps and 16,500 square feet of sidewalk; date is council award request, not proof of completion.
25 August 2026 council construction award agenda: City Council agenda recommended an LCR Earthwork & Engineering contract for $2.114 million, separate from Phase I.
Grade and reconstruct portions of channel, replace undersized culverts and relocate multiple utilities; physical construction not established by CEQA approval.
1 April 2026 CEQA determination filed: San Bernardino Flood Control District filed a determination for the proposed 2.97-mile, 100-year design-standard channel improvements.
Build a separate segment of major wastewater trunk infrastructure; bid receipt alone does not confirm actual construction start.
20 March 2026 bid opening: Water subcommittee says Phase II bids were received and construction was expected May 2026, with completion projected for early 2027.
Rezone specific plan areas for up to 735,185 square feet of light industrial uses and 13,000 square feet of commercial retail, with environmental documentation.
2026 city current-development project register: Rialto lists proposed Specific Plan changes and an approximately 485,000-square-foot industrial warehouse footprint.
Install a new storm drain and road restoration to reduce flooding; official project cost estimate $29 million.
October 2026 project construction notice: City construction portal confirms active work and temporary closures through 30 October 2026, with programme continuing into October 2027.
Audit, install and connect advanced water meters for improved reading and customer operations; early-2027 completion was a forecast.
11 February 2026 meter audit start: Water subcommittee reports Concord Services started citywide meter audit, with planned installation through late 2026.
Public projects and major development in Rialto, California, with separately sourced current, upcoming and completed records. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.