Latest documented evidence Selected dated project-owner milestones; this is not a live feed or confirmation that work happened today.
Find current projects Search 10 curated current project records, or open the historical archive .
Search project or location Project typeAll types Public facilities Planning & development Parks & public realm Roads & mobility
10 current projects
No projects match those filters.
Upcoming and preconstruction 6 selected projects
Planned, reviewed, approved or tendered. Forecast dates are not evidence that construction started.
Roads & mobility · Community engagement and planned construction Pavement, crossings, drainage and traffic safety upgrades.
24 September 2026: City scheduled a community information meeting about the street redesign and forecast a fall 2026 start.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Preconstruction and expected bid Street safety and active transportation upgrades on southern Pacific Avenue.
2 April 2026: Public Works presented corridor designs and anticipated fall 2026 construction.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Design / forecast start Separate northern section of the Pacific Avenue corridor renewal.
2026 project timeline: City published plans with an expected late-2026 construction start and late-2028 finish.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Preferred design and anticipated contract Safer bicycle and pedestrian corridor along Orange Avenue.
October 2025; 2026 programme: City selected Alternative 2 and forecast construction in autumn 2026 following design and bids.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Construction contract approved Replacement play equipment and accessible landscaped play area.
18 August 2026: Council approved award to Environmental Construction, Inc. for a renewed inclusive playground.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Bid review; award anticipated Renovation of a building for a year-round emergency shelter.
August 2026: City said bids had been assessed and recommended award would be submitted in autumn 2026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Documented construction 4 selected projects
Works that project owners identify as under construction; not a live on-site report.
Roads & mobility · Multi-segment roadway construction programme in progress More than five miles of Studebaker Road are being reconstructed for safer walking, cycling, public transport and road travel between 2nd Street and Carson Street.
April 2026: City published active phased-construction notices for Studebaker Road and Loynes Drive, with All American Asphalt as contractor. The five scheduled segments run on different timelines into 2027.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Construction documented Boat ramp, restroom and parking improvements.
August 2026: City photographs document ramp demolition, electrical work and completed abatement during ongoing works.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Commissioning and closeout reported New two-storey replacement fire station.
August 2026: City reported permanent electrical connection and commissioning underway; a September final certificate was forecast.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · Listed by owner as under construction 64-unit senior affordable housing development.
2026 development register: Owner's affordable-housing register lists armory conversion and new affordable apartments under construction.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Selected source-backed municipal, transport, housing and port-adjacent projects within Long Beach city limits, not an exhaustive inventory. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.