Water & utilitiesAugust 2026 township update says the late-2025-started drainage and pavement reconstruction between 14th Street and Teaberry Court was nearly complete, with landscaping outstanding.
Roads & mobilityJune 8 2026 township update reported a dozen roads repaved in recent weeks; broader resurfacing activity continues across the annual municipal road programme.
Roads & mobilityLakewood township engineering communications document a new phase of Route 9 improvements with overnight closures and traffic detours in 2026.
Water & utilitiesThe 2026 Lakewood township public works notices detail canvassing schedules and service line inspection/replacement works by New Jersey American Water.
Future projects
5 projects
Planned or in design or procurement; construction not yet confirmed.
Water & utilitiesLakewood Township MUA secured a $4.9m Water Bank loan in September 2026 to build a new public sanitary sewer conveyance system connecting Old Pine Acres homes now relying on septic; loan approval not construction.
Roads & mobilityLakewood engineering's 2026 notices include a May public-information meeting for Kennedy Boulevard and County Line Road improvements; design or consultation does not establish construction.
Water & utilitiesLakewood Engineer's published notice to bidders separately identifies improvements to Leigh Drive and an associated drainage easement; final award unverified.
Roads & mobilityTownship engineering publishes a named bid notice for sidewalks along West County Line Road and Prospect Street; physical completion unverified.
Roads & mobilityTownship's 2026 engineering inventory includes ongoing and newly planned pedestrian access around Central Avenue and the Lakewood–Jackson boundary; future connections are not conflated with the completed New Central Avenue segment.