Burlington Streetscapes
The city's October construction register lists improvements along MLK Jr Avenue from Kirkwood to Shelby and Prosser Road from MLK Jr Avenue to Holston Drive.
Source reviewed 1 Nov 2026
View project →Knoxville, Tennessee
A source-backed record of construction and planned development.
Sources reviewed 1 Nov 2026 · Selected projects, not a complete municipal register
6 projects
Construction documented by the project owner. Status is a dated research snapshot.
The city's October construction register lists improvements along MLK Jr Avenue from Kirkwood to Shelby and Prosser Road from MLK Jr Avenue to Holston Drive.
Source reviewed 1 Nov 2026
View project →Knoxville's October 2026 construction roster lists accessibility work to add or improve sidewalk curb cuts at selected resurfacing locations.
Source reviewed 1 Nov 2026
View project →The city's construction list identifies replacement of the leaking shingle roof at 1216 New York Avenue with a standing-seam metal roofing system.
Source reviewed 1 Nov 2026
View project →The October construction roster identifies replacement of aging signal infrastructure along Gay Street, with engineering by Gresham Smith.
Source reviewed 1 Nov 2026
View project →The city's construction register includes a 1.25-mile Pleasant Ridge Road scheme from Merchant Drive to the city limits with junction, drainage and shared-use path upgrades.
Source reviewed 1 Nov 2026
View project →Knoxville's construction roster includes the Sevier Avenue roundabout, rail crossing and streetscape improvements together with utility duct-bank relocation.
Source reviewed 1 Nov 2026
View project →4 projects
Planned or in design or procurement; construction not yet confirmed.
The October design register lists signal and fibre communications integration at 29 intersections on North Broadway, with bidding forecast for autumn 2026.
Source reviewed 1 Nov 2026
View project →The city is designing an integrated signal and fibre network for 47 Kingston Pike junctions from Metron Center Way to Huxley Road; winter 2028 is a projected bid date.
Source reviewed 1 Nov 2026
View project →A design-phase Washington Pike scheme between I-640 and Murphy Road includes staged lane geometry and two shared-use paths; spring 2027 bidding is forecast.
Source reviewed 1 Nov 2026
View project →The October design list records bicycle and pedestrian improvements along East Woodland Avenue between West Glenwood Avenue and North Broadway.
Source reviewed 1 Nov 2026