Latest documented evidence Selected dated project-owner milestones; this is not a live feed or confirmation that work happened today.
Find current projects Search 10 curated current project records, or open the historical archive .
Search project or location Project typeAll types Public facilities Planning & development Parks & public realm Roads & mobility Water & utilities
10 current projects
No projects match those filters.
Upcoming and preconstruction 7 selected projects
Planned, reviewed, approved or tendered. Forecast dates are not evidence that construction started.
Parks & public realm · Final design recorded; construction unverified Planned lakes and associated water systems in the Great Park.
9 September 2025: Great Park quarterly update listed the lakes as entering final design and scheduled work for mid-2026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Final design recorded Conversion of former military building into flexible event facilities.
9 September 2025: Quarterly update listed Building 369 among six Great Park projects approaching final design.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Final design recorded Landscaped perimeter and trails around developing Great Park sectors.
9 September 2025: City included Perimeter Park among projects entering final design, with anticipated mid-2026 construction.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Water & utilities · Procurement was forecast Water, drainage, electrical, telecommunications and other infrastructure serving Cultural Terrace West.
9 September 2025: City expected to solicit bids for wet and dry utility installation in October 2025, with work projected January 2026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Roads & mobility · Bid and works were projected Proposed grade-separated bridge for walking and cycling at Great Park.
9 September 2025: City identified a 227-foot pedestrian and bicycle bridge as nearing procurement, with construction then expected early 2026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Design and consultant development Permanent live performance venue planned for the Great Park.
9 September 2025: City placed the permanent amphitheater in final design and excluded it from the expected mid-2026 starts.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · Future affordable units listed Affordable homes within the Nova Apartments development.
1 October 2025: City listed 38 income-restricted apartments anticipated during 2026–2027.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Documented construction 3 selected projects
Works that project owners identify as under construction; not a live on-site report.
Public facilities · Construction recorded by owner Removal of legacy military infrastructure for future park development.
9 September 2025: City listed Phase 2 of runway, tarmac and subsurface utility demolition under construction, with November 2026 forecast completion.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · Developer construction and tenant announcements Twelve-acre neighbourhood retail and dining destination at the Great Park.
16 March 2026: Developer announced first wave of tenants at a planned 90,000-square-foot retail and dining destination.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Public facilities · Construction reported Municipal offices for park operations and public safety.
9 September 2025: City listed 11 connected modular office buildings and a secured EV-ready yard under construction.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Initial curated Irvine public infrastructure, Great Park and development records. Earlier owner schedules are treated as forecasts, not confirmation of today's site activity. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.