Completed freeway interchange connecting Ranchero Road to I-15, delivered under the $59 million Phase II corridor programme.
March 2015 City completion record: City's official corridor chronology confirms the highway interchange opened following completed Phase II works in March 2015.
FY2025–26 city certified construction completion: Hesperia FY2026–27 CIP project sheet explicitly says physical construction completed in FY2025–26 and only close-out continues in 2026–27.