Latest documented evidence Selected dated project-owner milestones; this is not a live feed or confirmation that work happened today.
Find current projects Search 9 curated current project records, or open the historical archive .
Search project or location Project typeAll types Planning & development Industry Parks & public realm Rail & transit Roads & mobility
9 current projects
No projects match those filters.
Upcoming and preconstruction 4 selected projects
Planned, reviewed, approved or tendered. Forecast dates are not evidence that construction started.
Roads & mobility · Planning and construction funding recorded Separated walking and cycling link along San Diego Bay.
2026 city project record: City reports a quarter-mile separated bikeway gap project, supported by Active Transportation Program construction funding.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Rail & transit · Historic feasibility study; fresh status unavailable Potential separation of light rail tracks from major streets.
17 January 2020: City published the Palomar Street grade-separation project report following 2017 corridor alternatives study.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · Planning notice issued Proposed town-centre development in the Cota Vera community.
10 September 2026: City issued a public notice of consideration for case PLN26-0026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Industry · Master-plan environmental update Future marina improvements and landside development within bayfront master plan.
29 January 2026: Port approved an update to the Bayfront Master Plan environmental impact report addressing project phasing and traffic mitigation.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Documented construction 5 selected projects
Works that project owners identify as under construction; not a live on-site report.
Roads & mobility · Construction commenced December 2024 Replacement and widening of a functionally obsolete river bridge.
December 2024: City reported construction started after an October 2024 contract award, with summer 2027 projected completion.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Construction underway since March 2025 Renovation of Chula Vista's oldest community park.
March 2025: City reports work began in March 2025 and the lower park is closed while amenities are upgraded.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Playground opened; splash pad and northern phase unfinished Phased expansion of Chula Vista's Harbor Park from about 12 to 25 acres, adding a public playground, splash pad, landscaped paths and more bayfront access.
14 October 2026: The Port of San Diego and Chula Vista opened Harbor Park's nautical playground to the public. The separate splash pad is scheduled for spring 2027, and northern landscape and walking connections remain in progress.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Parks & public realm · Listed by city among projects in construction Stabilisation and restoration works for park access.
October 2026 project register: Municipal Public Works project register includes Hilltop Park Improvements in construction.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Planning & development · City lists Phase 1 under construction First phase of a large educational and innovation district.
2026 city programme: City promotes a 553-acre university and innovation district, with Phase 1 described as under construction and delivery forecast fall 2026.
Source evidence reviewed 30 Oct 2026
View permanent record ↗ Curated Chula Vista infrastructure and Bayfront collection. Historic awards and forecasts are distinguished from verified site milestones. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.