ChaseDesk← Oregon cities

Bend, Oregon · Project encyclopedia

Projects in Bend, Oregon.

Find upcoming development and work underway. Every project keeps a permanent source-backed article and full history.

4 upcoming5 underway3 completed

Owner records reviewed 31 Oct 2026. Curated collection, not exhaustive.

Latest documented evidence

Selected dated project-owner milestones; this is not a live feed or confirmation that work happened today.

Find current projects

Search 9 curated current project records, or open the historical archive.

9 current projects

Upcoming and preconstruction

4 selected projects

Planned, reviewed, approved or tendered. Forecast dates are not evidence that construction started.

Roads & mobility · Design, programme, grant or planned project; site construction not confirmed

Butler Market Road Phase II Protected Bike/Ped Route

Build improved sidewalk and separated bike route and redesign Boyd Acres junction to modern safety standards.

2026 City phase sequencing statement: City separately schedules Phase II for January to fall 2027; Phase I Wells Acres roundabout is not counted as the new phase's completion.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Design, programme, grant or planned project; site construction not confirmed

Reed Market Road and 15th Street Roundabout Expansion

Expand partial roundabout into an intuitive two-lane layout with ADA-compliant crossing and safer cycling connections.

2026 detailed design schedule: City describes design completion targeted end 2026 and construction beginning early 2027, without works mobilisation today.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Design, programme, grant or planned project; site construction not confirmed

Hawthorne Bicycle and Pedestrian Bridge over US97

Create a dedicated active-travel overpass linking neighborhoods divided by the highway and railroad.

October 2026 owner construction roadmap: City 2026 construction register schedules a dedicated walking/cycling bridge for fall 2027 through fall 2028.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Design, programme, grant or planned project; site construction not confirmed

Aune Street Extension, Third Street to Bond Street

Build missing street connection supporting pedestrian, cycle and vehicle travel between Third and Bond.

October 2026 owner construction programme: City lists a new east–west link to begin in early 2027 with completion targeted autumn, not verified as started.

Source evidence reviewed

View permanent record ↗

Documented construction

5 selected projects

Works that project owners identify as under construction; not a live on-site report.

Water & utilities · Owner documents work or contractor; formal completion unverified

Second Street and Lafayette Waterline Replacement

Replace undersized 12-inch cast-iron main with 18-inch ductile iron pipe, improving distribution between Awbrey and Pilot Butte reservoirs.

July 2026 construction window: City confirms June 25 preconstruction open house followed by July–October 2026 works; no independent completion notice was located.

Source evidence reviewed

View permanent record ↗
Water & utilities · Owner documents work or contractor; formal completion unverified

Cooley Sewer Improvements and Phoenix Pump Decommissioning

Build trunk sewer and residential laterals to enable septic connections while taking an old pump station out of service.

13 July 2026 physical works notice: City states construction began early July with trenching for a new gravity main and planned decommissioning of the Phoenix pump station.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Owner documents work or contractor; formal completion unverified

Galveston Corridor Safety Project Phases 2–3

Improve Galveston crossings, water-pressure hardware, accessible sidewalk, street lighting, paving and protected cycling across separate phases.

Fall 2026 owner phased construction update: City expressly marks Phase 1 complete and schedules a second-stage raised crossing plus pressure-reducing valve, followed by 2027 reconstruction.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Owner documents work or contractor; formal completion unverified

Neff and Norton Pedestrian/Bicycle Key Routes

Build shared-use path, school-area crossings and protected/buffered walking/cycling links along three connected key-route projects.

June 2026 Phase I construction start: City schedules Phase I construction from east of Larkspur Trail to Eagle Road starting June 2026, with ODOT retaining later segments.

Source evidence reviewed

View permanent record ↗
Roads & mobility · Owner documents work or contractor; formal completion unverified

Midtown Crossings: Franklin Avenue Underpass Improvements

Rebuild Franklin Avenue undercrossing drainage, accessibility and cycling/pedestrian connections as part of Midtown Crossings.

August 2026 construction phase announcement: Citywide works map records Franklin Avenue undercrossing closure for stormwater and multimodal improvements through May 2027.

Source evidence reviewed

View permanent record ↗

Completed projects remain accessible

Historical project records are preserved for research without crowding the current-project funnel.

Bend historical archive · 3 records

Verified openings and completions, with original evidence and permanent articles.

Open archive ↗

Public infrastructure, capital schemes and source-backed completed projects in Bend, Oregon, with distinct underway, upcoming and historic records. Confidence percentages are editorial, not calibrated. Project pages distinguish source dates, forecast dates and research checks.