Ray Road & Dobson Road Intersection Improvements
Intersection improvement project with active bidding and separate utility relocation work.
These archived records remain available for reference, not current buying opportunities.
What changed
Chandler issued Addendum No. 2 on September 29 to an active construction bid due October 15. Council also approved a $1.60 million SRP agreement on September 17 for irrigation-facility relocation tied to the project.
Why it matters for sitework
A live bid with a recent addendum is directly actionable for civil/site contractors and suppliers.
Likely work
Near-term bidding opportunity with utility relocation and roadway civil scope.
Likely scope, not confirmed contract scope: Likely roadway excavation, utility/irrigation relocation, grading, drainage, paving and associated civil work. Exact prime bid scope should be checked in the solicitation documents.
Known participants
- Owner: City of Chandler
- Developer / responsible party: Unknown
- Architect / applicant: Unknown
- Engineer: Unknown
- GC: Unknown
Chronology
- Addendum No. 1 issued for the construction bid.
- Mandatory pre-bid conference.
- Council approved the $1,600,430 SRP construction-services agreement tied to intersection improvements.
- Addendum No. 2 issued.
- Bid submission deadline (future as of backfill).