Historic first-stage park facility improvements, distinct from the uncompleted later $755,157 Phase II programme.
May 2026 PY2026 action-plan accomplishment review: City's 2026 CDBG action-plan narrative explicitly records the initial $1 million Friendship Park improvement activity as completed, and distinguishes a separate second phase still in design.
Replace the senior centre roof and HVAC plant, including asbestos abatement and upgraded mechanical systems; historic works completed, not active construction.
2026 city community-development completed-work report: City's PY2026 Action Plan explicitly declares replacement roof and HVAC complete, with project under budget by approximately $205,000.