Latest verified development
8 June 2026 city project updateFargo's June engineering update reported physical foundation work underway on the Belmont levee and floodwalls.
Project in numbers
About the project
The owner planned levees to protect at river stages up to 44 feet, with relocation of two homes and approximately 80 replacement trees. Autumn 2026 finish remains an expectation, not a verified acceptance.
Verified development history
- 3 March 2026
The city published Phase 3 works beginning in April from the plant toward South River Road and a planned floodwall at 1458 South River Road.
Original evidence ↗ - 8 June 2026
City Engineer recorded foundations underway at the Belmont levee and floodwall construction site.
Original evidence ↗
What happens next
Recheck FargoStreets or the project owner before changing status, projected completion or funding.
What remains uncertain
Owner evidence reviewed 31 October 2026. A listed work-zone completion date is not a certificate of completion; planning, site selection, grant money and design do not establish site construction. Editorial confidence indicates reliability of documentation, not probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Original city or lead-agency project description and status ↗
- Supporting project-owner updates, decision or capital programme ↗
92% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.