Completed projects
3 permanent historical records
Roads & mobility · Engineering staff certified contract physically complete before January 2026 final-acceptance requestCompleted resurfacing, accessible sidewalks, signal modifications and utility adjustments over three-quarters of a mile.
5 January 2026: City's acceptance report states work was completed per contract and staff recommended notice of completion.
Source evidence reviewed
View permanent record ↗ Roads & mobility · City engineering report identifies construction complete, final acceptance sought January 2026Completed street pavement renewal and traffic signal / curb repair.
5 January 2026: Staff report certifies approximately half-mile asphalt and associated concrete works complete.
Source evidence reviewed
View permanent record ↗ Roads & mobility · Final acceptance item scheduled March 2026 with reported final costCompleted first portion of Shaw Avenue widening with street utilities and signalling.
16 March 2026: City Council published final acceptance and completion item for Phase I.
Source evidence reviewed
View permanent record ↗ Projects move to this archive only after original evidence of completion or opening. Their article URLs do not change.
Current Clovis projectsUpcoming work, plans and documented construction.
Explore current ↗