Vancouver · Public facilities

Public Works Operations Campus

Construction began in 2025 on a new 32-acre municipal operations campus; major phases continue through 2028.

Construction documented in owner or construction register; current site activity is not continuously monitoredEvidence: 2026 owner works programme · Reviewed 31 October 2026

Latest verified development

2026 owner works programme

City lists ground improvement, 195 geo-exchange wells and foundation/utility works in the construction programme.

View original record ↗

Project in numbers

32-acre campusProject scale or scope
195 geo-exchange wellsPublished scheme detail
2028 targetDocumented milestone or forecast

About the project

Construction began in 2025 on a new 32-acre municipal operations campus; major phases continue through 2028. This is a municipality-level project record; published schedules are not proof of a later physical milestone.

Verified development history

  1. 2026 owner works programme

    City lists ground improvement, 195 geo-exchange wells and foundation/utility works in the construction programme.

    Original evidence ↗
  2. 31 October 2026 evidence review

    Checked the owner project notice and distinguished confirmed events from forecast works or opening dates.

    Original evidence ↗

What happens next

Next owner construction, procurement or completion update not yet independently verified.

What remains uncertain

Checked 31 October 2026. Source publication and milestone dates may differ. The status reflects documentary evidence, not live site inspection.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

88% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 31 October 2026.