Claims & confidence Expand for evidence
Percentages are dated editorial judgements of documentary evidence support, not statistically calibrated probabilities. A scheduled event or construction estimate is not a completion record.
- 95% confidenceContractor site mobilisation began 1 June 2026City project milestones specify mobilisation.
- 95% confidenceConstruction was underway in the week of 19 October 2026City's weekly activity log reports ledge concrete pours and ramp rebar.
- 95% confidenceSkate features, concrete, electrical and landscaping are within the project scopeCity scope and works list.
- 70% confidenceCity targets December 2026 completionForecast, not an observed completion.
95% directly documented in an original or retrospective source; 85–90% strong but date-limited; 60–80% forecast or conditional. Unverified means no documentary support was established, not a numeric probability. Original sources ↓
- Location
- 700 W. Cushing Street, Tucson 95% confidence
- Classification
- Parks · Skateboarding 95% confidence
- Source-backed stage
- Physical construction verified in week of 19 October 90% confidence
- Project / reference
- Cushing Street Skate Park / I-10 underpass 95% confidence
- Source event
- Week of 19 October 2026 90% confidence
- Directory
- Ongoing projects 95% confidence
Project timeline
Recorded activity, projections and unknown milestones are kept separate. This is a dated research snapshot, not automatic real-time tracking.
- 24 March 2026Recorded
Intergovernmental agreement executed 95% confidence
City, ADOT and federal authorisation milestone.
- 1 June 2026Recorded
Site mobilisation starts 95% confidence
City's construction chronology.
- 30 June 2026Recorded
Groundbreaking event 95% confidence
City calendar and record.
- Week of 19 October 2026Recorded
Ledge concrete and ramp preparations 95% confidence
Weekly construction log identifies physical site work.
- December 2026Scheduled / forecast
Projected park completion 70% confidence
Municipal estimated date only.
Project history and evidence
Tucson's Cushing Street project turns space under Interstate 10 into a public skate park. The city's dated activity log identifies grading, concrete, utility and skate-feature work, rather than merely a proposal. 90% confidence
The 19 October 2026 update reports concrete work and ramp reinforcement, while a December completion remains an estimate. The park was not documented as open at this review. 90% confidence
Evidence boundary: Claims were reviewed 23 October 2026. A project schedule, public budget, land transaction or opening announcement is not proof the predicted construction or opening occurred. Primary sources are linked below.