SE 29th Street Butcher Creek and Utilities

Road widening, drainage, utilities and signal improvements within one corridor construction package.

Documented 2026 active programme, works or owner's progress; verify specific site phaseEvidence: 6 October 2026 closure · Reviewed 31 October 2026

Latest verified development

6 October 2026 closure

City announced six-month closure to replace Butcher Creek culvert and undertake road and water/sewer works.

View original record ↗

Project in numbers

Butcher Creek box culvertDocumented scope or milestone
SE 29th from Kansas Avenue to Adams StreetProject location
Current / activeChaseDesk evidence stage

About the project

Road widening, drainage, utilities and signal improvements within one corridor construction package.

Verified development history

  1. 2026 agency programme or project history

    The original owner or responsible agency records this named project and its scope. Where status was an announcement or finance entry, that does not by itself establish construction.

    Original evidence ↗
  2. 6 October 2026 closure

    City announced six-month closure to replace Butcher Creek culvert and undertake road and water/sewer works.

    Original evidence ↗

What happens next

Verify a dated owner completion or construction update before changing the stage.

What remains uncertain

Reviewed 31 October 2026. Source dates and target dates are not the same as verified site milestones. Where the evidence is a programme, budget, procurement or start notice, current physical progress and acceptance remain unverified. The confidence value describes editorial evidence strength, not probability of completion.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

84% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 31 October 2026.