Tampa · Public facilities

Tampa Convention Center Electrical Switchgear Modernisation

Electrical-switchgear replacement and modernisation programme for Tampa Convention Center, with City-issued electrical schedules and condition assessment.

Future: procurement Bid 26-C-00026 gained a bid tabulation 3 November; contract award, outage schedule and field installation not confirmed.Evidence: 3 November 2026 Tampa construction tender bid-tabulation update · Reviewed 4 November 2026

Latest verified development

3 November 2026 Tampa construction tender bid-tabulation update

The City updated construction bid 26-C-00026 at 4:05 pm 3 November, listing the tender bid tab and electrical schedules and condition assessment. Tender opening was scheduled 1:30 pm the same day; a bid tab is not a project award.

View original record ↗

Project in numbers

26-C-00026Owner construction bid
3 Nov 2026Bid-tabulation update
211 S Franklin StConvention Center address

About the project

Electrical distribution and switchgear equipment renewal at the convention centre, informed by an electrical study, technical schedules and facility condition assessment. Planned vendor, scope of planned shutdowns, total cost and installation window have not been verified from an awarded contract.

Verified development history

  1. 31 August 2026 City procurement posted

    The City opened construction Bid 26-C-00026, supported by switchgear electrical study and condition assessment.

    Original evidence ↗
  2. 21 September 2026 pre-bid meeting scheduled

    Tampa advertised a morning pre-bid session at the Convention Center, not a project commencement.

    Original evidence ↗
  3. 3 November 2026 bids scheduled and tab posted

    Owner tender page shows the date of bid opening and updated bid tabulation documents.

    Original evidence ↗

What happens next

Verify award and any notice to proceed or electrical shutdown approvals before recording construction activity.

What remains uncertain

First bid posted 31 August 2026; the substantive 3 November update is release of the bid tabulation. None of the public tender dates proves that switchgear has been installed or contracted.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

97% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 4 November 2026.