Latest verified development
31 October 2026 segment status reviewThe owner explicitly calls the 1.3-mile Grand and Spring corridor under construction; a spring 2027 opening is a forecast.
Project in numbers
About the project
Great Rivers Greenway began construction on the Fairground Park to Page North Connector. The owner explicitly calls the 1.3-mile Grand and Spring corridor under construction; a spring 2027 opening is a forecast.
Verified development history
- August 2025 start
Great Rivers Greenway began construction on the Fairground Park to Page North Connector.
Original evidence ↗ - 31 October 2026 segment status review
The owner explicitly calls the 1.3-mile Grand and Spring corridor under construction; a spring 2027 opening is a forecast.
Original evidence ↗
What happens next
Check the agency's spring 2027 opening announcement.
What remains uncertain
Evidence reviewed 31 October 2026. The first timeline entry is the agency's dated or named documentary stage; the review date is not a claim of new field activity. An estimated opening or construction date does not prove a milestone happened. A programme labelled current can lag actual field status. Check the linked original owner record for later changes. Editorial confidence assesses the documents, not probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Official original project announcement, programme or status register ↗
- Additional official agency project context or programme ↗
97% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.