31 October 2026 source reviewGreat Rivers Greenway calls the one-mile link design-stage, with 2028-2029 delivery planning and a federal grant.
Project in numbers
About the project
The project will link Forest Park's paths to Cortex via the Kingshighway underpass. Great Rivers Greenway calls the one-mile link design-stage, with 2028-2029 delivery planning and a federal grant.
Verified development history
- 2026 greenway route planning
The project will link Forest Park's paths to Cortex via the Kingshighway underpass.
Original evidence ↗ - 31 October 2026 source review
Great Rivers Greenway calls the one-mile link design-stage, with 2028-2029 delivery planning and a federal grant.
Original evidence ↗
What happens next
Verify the corridor's final design and a later contract award.
What remains uncertain
Evidence reviewed 31 October 2026. The first timeline entry is the agency's dated or named documentary stage; the review date is not a claim of new field activity. An estimated opening or construction date does not prove a milestone happened. A programme labelled current can lag actual field status. Check the linked original owner record for later changes. Editorial confidence assesses the documents, not probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Official original project announcement, programme or status register ↗
- Additional official agency project context or programme ↗
89% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.