Latest verified development
2026 capital projects updateSavannah says external masonry, steel cleaning and restoration are underway with spring 2027 forecast completion.
Project in numbers
About the project
City began masonry repair, stabilising old building elements and controlled demolition for heritage preservation. Savannah says external masonry, steel cleaning and restoration are underway with spring 2027 forecast completion.
Verified development history
- Spring 2026 physical mobilisation
City began masonry repair, stabilising old building elements and controlled demolition for heritage preservation.
Original evidence ↗ - 2026 capital projects update
Savannah says external masonry, steel cleaning and restoration are underway with spring 2027 forecast completion.
Original evidence ↗
What happens next
Seek a later, project-specific field milestone or practical completion notice before revising stage.
What remains uncertain
Project records reviewed 31 October 2026. Documentary programme updates are not proof of work on every individual parcel. Planned dates are estimates, not completed events. If a project has preliminary design or contract award without documented mobilisation, it is Future. Historical phase claims require an explicit completion or opening. Editorial confidence concerns evidence quality, not delivery probability.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Original project-specific authority announcement, agenda or source page ↗
- Supporting official agency register, programme or phase source ↗
91% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.