Salinas · Roads & mobility

East Boronda Road Congestion Relief Phase 1

First phase of a larger four-roundabout Boronda Road widening programme.

Granite contractor works; late-2026 forecast completionEvidence: 2026 construction phase update · Reviewed 30 October 2026

Latest verified development

2026 construction phase update

Owner reports the McKinnon roundabout project in Stage 2 with a temporary McKinnon closure.

View original record ↗

Project in numbers

Nov 2024Construction began
Stage 2Owner's reported work phase
Late 2026Anticipated completion

About the project

Construction began November 2024. Phase 1 includes McKinnon Street roundabout and associated lanes, pedestrian paths and drainage. Future phases must not be labelled as already constructed.

Verified development history

  1. November 2024

    City confirms Granite Construction began Phase 1.

    Original evidence ↗
  2. 2026 municipal CIP

    Capital programmes continue to list the Boronda project.

    Original evidence ↗

What happens next

Check owner completion and reopening notices rather than assume late-2026 forecast.

What remains uncertain

A capital-project inventory identifies an official scheme but not necessarily active construction. Dates quoted from grant, environmental or budget documents are document milestones; actual site mobilisation, completion and opening require separate dated evidence.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

87% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 30 October 2026.