Latest verified development
2026 construction phase updateOwner reports the McKinnon roundabout project in Stage 2 with a temporary McKinnon closure.
Project in numbers
About the project
Construction began November 2024. Phase 1 includes McKinnon Street roundabout and associated lanes, pedestrian paths and drainage. Future phases must not be labelled as already constructed.
Verified development history
- November 2024
City confirms Granite Construction began Phase 1.
Original evidence ↗ - 2026 municipal CIP
Capital programmes continue to list the Boronda project.
Original evidence ↗
What happens next
Check owner completion and reopening notices rather than assume late-2026 forecast.
What remains uncertain
A capital-project inventory identifies an official scheme but not necessarily active construction. Dates quoted from grant, environmental or budget documents are document milestones; actual site mobilisation, completion and opening require separate dated evidence.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Original City of Salinas project or owner notice ↗
- Supporting municipal transport, capital or event record ↗
87% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 30 October 2026.