Latest verified development
31 July 2026 contractor construction updateMunicipal weekly status identifies continuing underground sanitary tunnel repairs and new or replacement tunnel-shaft construction near West 7th and Chestnut, with lane restrictions maintained.
Project in numbers
About the project
July–November works include a new sanitary shaft, replacement shaft and tunnel repairs with one vehicle lane each direction. Planned later activity remains conditional.
Verified development history
- 26 June 2026
City reported sewer-shaft construction commenced at the Kellogg Boulevard end and Walnut Street sewer work closed out.
Original evidence ↗ - 31 July 2026 contractor construction update
Municipal weekly status identifies continuing underground sanitary tunnel repairs and new or replacement tunnel-shaft construction near West 7th and Chestnut, with lane restrictions maintained.
Original evidence ↗
What happens next
Review the next project-specific construction update for an owner-confirmed change in stage.
What remains uncertain
Editorial document review 31 October 2026. Forecast start and finish dates do not establish physical commencement or completion; document confidence measures source support, not a probabilistic prediction.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
95% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.