Transportation · Road and bridge design

El Mirage Road extension: Loop 303 to Jomax

A planned four-lane north Peoria road extension with bridge crossings over McMicken Wash and Beardsley Canal. 85% confidence

Sources reviewed 23 October 2026 · Primary evidence

Claims & confidence Expand for evidence

Scores represent editorial evidence confidence as of the source-review date, not calibrated statistical probabilities. Evidence of a city announcement differs from proof that a prediction came true.

  • 95% confidenceThe project would widen El Mirage Road and add two watercourse crossingsCity-coordinated project portal scope.
  • 95% confidenceADOT issued a Finding of No Significant Impact in December 2025Official project portal documents milestone.
  • 95% confidenceThe project advanced into final design after environmental reviewCity-coordinated project portal.
  • 65% confidenceConstruction may begin as early as 2028Project forecast; start and bid access are not verified.

95% directly documented by original evidence; 85–90% strong but time-limited; 60–80% forecast/conditional. 'Not verified' means evidence is missing, not that an event has a fabricated probability. Read sources ↓

Location
El Mirage Road corridor between Loop 303 and Jomax Road, Peoria 95% confidence
Classification
Transportation · Road and bridge design 95% confidence
Source-backed stage
Environmental approval issued; final design stage, no physical start evidenced 85% confidence
Project / reference
El Mirage Road Extension 95% confidence
Source event
December 2025 environmental finding and 2026 project update 90% confidence
Directory
Future projects 95% confidence

Project timeline

Dated records, schedules and unverified events are kept separate. No automatic live tracking or current site visit is claimed.

  1. December 2025Recorded

    Environmental Finding of No Significant Impact issued 95% confidence

    Official Peoria and ADOT-coordinated project portal.

  2. Spring 2026Recorded

    Final design phase announced 90% confidence

    Municipal study/design update, not construction.

  3. Fall 2027Scheduled / forecast

    Final design completion anticipated 75% confidence

    Date is a forecast.

  4. 2028 or laterScheduled / forecast

    Earliest indicated construction start 65% confidence

    Not a confirmed contract or mobilisation.

Project history and evidence

Peoria, ADOT and regional agencies are advancing an El Mirage Road connection north from Loop 303 to Jomax Road. Planned works include a median-separated arterial, bridges and intersections with walking and cycle facilities. 85% confidence

The project's design/environmental portal confirms environmental clearance and movement into final design. Nothing in that evidence establishes a construction notice to proceed as of 23 October 2026. 85% confidence

Evidence boundary: The sources were reviewed 23 October 2026. A dated project announcement, capital appropriation or forecast alone does not prove physical commencement, active bid availability, opening or final completion.