Claims & confidence Expand for evidence
Scores represent editorial evidence confidence as of the source-review date, not calibrated statistical probabilities. Evidence of a city announcement differs from proof that a prediction came true.
- 95% confidenceThe project would widen El Mirage Road and add two watercourse crossingsCity-coordinated project portal scope.
- 95% confidenceADOT issued a Finding of No Significant Impact in December 2025Official project portal documents milestone.
- 95% confidenceThe project advanced into final design after environmental reviewCity-coordinated project portal.
- 65% confidenceConstruction may begin as early as 2028Project forecast; start and bid access are not verified.
95% directly documented by original evidence; 85–90% strong but time-limited; 60–80% forecast/conditional. 'Not verified' means evidence is missing, not that an event has a fabricated probability. Read sources ↓
- Location
- El Mirage Road corridor between Loop 303 and Jomax Road, Peoria 95% confidence
- Classification
- Transportation · Road and bridge design 95% confidence
- Source-backed stage
- Environmental approval issued; final design stage, no physical start evidenced 85% confidence
- Project / reference
- El Mirage Road Extension 95% confidence
- Source event
- December 2025 environmental finding and 2026 project update 90% confidence
- Directory
- Future projects 95% confidence
Project timeline
Dated records, schedules and unverified events are kept separate. No automatic live tracking or current site visit is claimed.
- December 2025Recorded
Environmental Finding of No Significant Impact issued 95% confidence
Official Peoria and ADOT-coordinated project portal.
- Spring 2026Recorded
Final design phase announced 90% confidence
Municipal study/design update, not construction.
- Fall 2027Scheduled / forecast
Final design completion anticipated 75% confidence
Date is a forecast.
- 2028 or laterScheduled / forecast
Earliest indicated construction start 65% confidence
Not a confirmed contract or mobilisation.
Project history and evidence
Peoria, ADOT and regional agencies are advancing an El Mirage Road connection north from Loop 303 to Jomax Road. Planned works include a median-separated arterial, bridges and intersections with walking and cycle facilities. 85% confidence
The project's design/environmental portal confirms environmental clearance and movement into final design. Nothing in that evidence establishes a construction notice to proceed as of 23 October 2026. 85% confidence
Evidence boundary: The sources were reviewed 23 October 2026. A dated project announcement, capital appropriation or forecast alone does not prove physical commencement, active bid availability, opening or final completion.