Latest verified development
September 2026 project updateCity's third construction update covers June–August 2026 bridge columns, embankment settlement and railway crossing work.
Project in numbers
About the project
Grade-separation project requires Union Pacific coordination, a new bridge, railway clearances, signal/intersection rebuilding and relocation of numerous utilities.
Verified development history
- October 2024
City awarded construction contract after environmental clearance and acquisition of rail/road rights.
Original evidence ↗ - March 2025
Main construction commenced, with retaining-wall and substructure works subsequently documented.
Original evidence ↗
What happens next
December 2028 forecast, not completed
What remains uncertain
The cited milestone is a dated documentary record; projected dates are not confirmation of completed works.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
95% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 30 October 2026.