Madison, Wisconsin · Public facilities

Madison South District Police and Evidence Operations Facility

Planned colocation of Madison's South District Police station and citywide police property and evidence functions at 2120 Fish Hatchery Road.

FutureEvidence: 5 October 2026 municipal predesign update · Reviewed 8 November 2026
Project ownerCity of Madison Engineering / Madison Police DepartmentAs named in reviewed project records
Proposed civic site2120 Fish Hatchery RdFrom linked evidence
Evidence/storage consolidation4 sitesFrom linked evidence

Project intelligence

Verified evidence first; assumptions labelled

Latest verified development

Documented project record5 October 2026 municipal predesign update

Madison's October design update describes the former Town of Madison Town Hall site in active predesign, including space needs, room schedules and preliminary site planning. Engberg Anderson Architects was named as the selected architectural firm in the City's April update; construction contract award has not been established.

View original record ↗

Verified development history

5 documented entries

  1. 5 August 2025

    City advertised architectural and engineering consultant solicitation RFP 14030-0-2025-BP for the proposed South District Police and Evidence Facility.

    Original evidence ↗
  2. 19 September 2025

    City's posted A/E proposal due date; proposals underwent review. This is not a construction contractor bid.

    Original evidence ↗
  3. 6 April 2026 owner design update

    Madison identified Engberg Anderson Architects as the selected A/E firm, while final A/E contract approvals remained under review.

    Original evidence ↗
  4. 5 October 2026 predesign update

    City reported predesign space programming, conceptual test-fit and site-plan work, with a later schematic-design phase projected; no building mobilisation was announced.

    Original evidence ↗
  5. 8 November 2026 editorial verification

    Owner project register remains In Design. Project first documented permanently in ChaseDesk with Future classification, not dated as newly launched in November.

    Original evidence ↗

Project in numbers

2120 Fish Hatchery RdProposed civic site
4 sitesEvidence/storage consolidation
Q1 2029Forecast construction start
Q4 2030Forecast completion

The project explained

Purpose, scope and context

The proposal would relocate the South District Police operations from Hughes Place and consolidate police property, evidence and storage operations currently spread across four sites, with adjacent park-space concepts. At the reviewed 2026 date the project remains predesign, with no contractor tender or physical building construction.

What happens next

Foreseeable developments are not verified outcomes

Predesign completion was targeted for November 2026, schematic design for December 2026–May 2027, first construction bid advertising for Q3 2028, anticipated construction Q1 2029, and completion Q4 2030. All are forecasts; no building contract or construction start is verified.

Documented trade work packages

Potential scopes, not awarded subcontracts

These scopes are described in original records. No subcontract allocations are inferred from the total project budget; scopes may overlap and must not be added together.

Architectural space programming and police facility planning

Engberg Anderson Architects was selected for architectural/engineering work. The predesign phase includes space-needs analysis, room data sheets and test-fit studies to accommodate the South District Police function and consolidated evidence operations; no design contract value is asserted.

Original work-scope evidence ↗

Preliminary site and adjacent park planning

The owner describes conceptual site drawings for the former Town Hall land and adjacent park-space design features. This is current design work, not a construction package award.

Original work-scope evidence ↗

Future police and evidence facility construction

The City anticipates a construction solicitation in 2028 and physical delivery from 2029 to 2030. The future building works are a documented planned scope; exact trades and contractors remain unknown.

Original work-scope evidence ↗

What remains uncertain

Official City project dates are planning projections, not funded contract awards or construction starts. The April owner update identifies Engberg Anderson as selected for design but says contract approvals were then in review, so final executed design fee is not stated. No construction costs or separate work-package awards are inferred.

Official maps, designs and site visuals

Sources and documents

Linked original evidence remains available