Madison · transport

Capital City Path Segments 4–6, Vondron Road to I-39/90

Extend the shared-use Capital City Path east along the railroad corridor from Vondron Road towards I-39/90.

Tree-clearing preparatory contract awarded 4 November; main path still In Design and not under constructionEvidence: 4 November 2026 City of Madison enabling contract award · Reviewed 6 November 2026

Latest verified development

4 November 2026 City of Madison enabling contract award

Madison Engineering confirmed Interstate Tree Landscaping Company had been awarded preparatory tree removal for Capital City Path phases 5 and 6. Clearing is forecast 16–27 November; main path construction remains scheduled 2027–2028.

View original record ↗

Project in numbers

2027–2028Expected principal construction
16–27 Nov 2026Forecast vegetation works
Vondron–I-39/90Corridor limits

About the project

New walking and cycling route with staged vegetation removal and a paved trail segment, coordinated with Dane County's adjoining Glacial Drumlin Trail extension. Preliminary clearing contract is separate from main trail construction.

Verified development history

  1. 28 May 2026 scope and partnership

    City published 2027–2028 pathway extension programme linking with Dane County Glacial Drumlin Trail works.

    Original evidence ↗
  2. 10 September 2026 preparatory tender

    Madison public works recorded a tree removal tender for Capital City Path phases 5 and 6.

    Original evidence ↗
  3. 4 November 2026 preparatory contract award

    City announced Interstate Tree Landscaping Company selected for vegetation removal forecast 16–27 November, with principal pathway work planned for 2027–2028.

    Original evidence ↗

What happens next

Tree removal anticipated 16–27 November 2026; main pathway work 2027 to summer 2028 (owner projections). No opening confirmed.

What remains uncertain

City page still marks project In Design. Owner-confirmed November 4 contract award covers tree removal only; neither November clearing nor main path physical work is confirmed to have happened by November 6.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

96% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 6 November 2026.