Latest verified development
Fall 2026 progress updateThe owner reports clarifier-channel biofilter and carbon adsorption construction nearly complete, with the north system operating and south startup pending.
Project in numbers
About the project
Installation of biotrickling filters, carbon adsorbers and permanent hydrogen sulfide monitoring. The City retained Webster Environmental Associates to determine needed wastewater odor-control upgrades.
Verified development history
- 2024 odor-control engineering commission
The City retained Webster Environmental Associates to determine needed wastewater odor-control upgrades.
Original evidence ↗ - Fall 2026 progress update
The owner reports clarifier-channel biofilter and carbon adsorption construction nearly complete, with the north system operating and south startup pending.
Original evidence ↗
What happens next
Confirm commissioning of the south system and full project closeout.
What remains uncertain
Original owner material reviewed 31 October 2026. The evidence is dated and may lag on-site changes. Design, funding, contract award and future dates are not proof of a construction start. Completion is recorded only where explicitly confirmed; editorial confidence measures documentary support, not the probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Original owner project update, notice or engineering register ↗
- Supplementary agency project context, capital programme or status ↗
94% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.