Latest verified development
31 August 2026 city updateCity reports phase one complete, phase two partly built and Ward and O'Brien intersection still closed for work.
Project in numbers
About the project
Ward Road roadway construction began with intersection closure and water-main and storm-sewer works. City reports phase one complete, phase two partly built and Ward and O'Brien intersection still closed for work.
Verified development history
- 13 February 2026 construction start
Ward Road roadway construction began with intersection closure and water-main and storm-sewer works.
Original evidence ↗ - 31 August 2026 city update
City reports phase one complete, phase two partly built and Ward and O'Brien intersection still closed for work.
Original evidence ↗
What happens next
Verify full road reopening separately from the partial July roundabout opening.
What remains uncertain
Evidence reviewed 31 October 2026. The first timeline entry is the agency's dated or named documentary stage; the review date is not a claim of new field activity. An estimated opening or construction date does not prove a milestone happened. A programme labelled current can lag actual field status. Check the linked original owner record for later changes. Editorial confidence assesses the documents, not probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Official original project announcement, programme or status register ↗
- Additional official agency project context or programme ↗
97% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.