Hillsboro · Roads & mobility

Bridge over Brookwood Crescent Park Greenway

Plan a foot/cycle bridge across Brookwood Parkway to close a regional Crescent Park Greenway trail connection.

Design, programme, grant or planned project; site construction not confirmedEvidence: 28 May 2026 design option selection · Reviewed 31 October 2026

Latest verified development

28 May 2026 design option selection

Parks & Recreation Commission chose the Crescent Arch concept, allowing only 30% design and cost estimates; future construction depends on funding.

View original record ↗

Project in numbers

30% designOwner-reported project geography, identifier or scope
Crescent ArchOwner figure or construction window
Funding-dependentEvidence-specific phase qualifier

About the project

Plan a foot/cycle bridge across Brookwood Parkway to close a regional Crescent Park Greenway trail connection. The recorded project stage is a source-backed snapshot. Budget approvals, projected finishes or bid-stage announcements are not formal acceptance.

Verified development history

  1. 28 May 2026 design option selection

    Parks & Recreation Commission chose the Crescent Arch concept, allowing only 30% design and cost estimates; future construction depends on funding.

    Original evidence ↗
  2. 31 October 2026 editorial status review

    Construction-start and future delivery dates have not been inferred beyond cited owner milestones.

    Original evidence ↗

What happens next

Review a newer dated municipality notice, physical contractor record or formal completion report before advancing status.

What remains uncertain

Research checked 31 October 2026. Public owner programmes are not live site tracking and some forecast dates may have passed without a published final acceptance. Confidence is editorial evidence assessment, not a predicted project completion probability.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

88% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 31 October 2026.