Latest verified development
6 February 2026 owner progress announcementINDOT reported west Lloyd construction packages around 45 percent complete in February 2026, with further improvement contracts remaining.
Project in numbers
About the project
Do not confuse west-side contracts expected to finish in 2026 with separate planned 2027 pavement replacement between Ingle and Wabash avenues.
Verified development history
- 2024 main contract award
INDOT began delivery of staged Lloyd4U reconstruction on the west side.
Original evidence ↗ - February 2026 construction progress
INDOT reported major west Lloyd contracts approximately 45% built with forecast later completion.
Original evidence ↗
What happens next
Recheck owner updates and contracts before revising stage.
What remains uncertain
Reviewed 31 October 2026; a past construction forecast is not confirmation of actual completion. Editorial confidence measures documented evidence quality, not probability of delivery.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
- Project-owner plan, dated update, or original agency project document ↗
- Supporting agency, project partner or original municipal record ↗
90% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 31 October 2026.