Elk Grove · Roads & mobility

Kammerer Road Extension, Bruceville to I-5

Proposed new road connection linking western Elk Grove with Interstate 5.

Design and land acquisition progressingEvidence: 18 October 2026 · Reviewed 30 October 2026

Latest verified development

18 October 2026

City Manager reports a 65% on-system design package submitted to Caltrans and active right-of-way acquisition.

View original record ↗

Project in numbers

2 lanesPlanned road
65%Submitted design-package stage (not construction)
I-5Western connection

About the project

Planned two-lane road extension requires environmental approval, highway engineering, land acquisition and eventual construction funding. Design submission must not be described as physical road construction.

Verified development history

  1. 20 February 2025

    Project identified in council strategic priorities with design and acquisition actions.

    Original evidence ↗
  2. 18 October 2026

    65% on-system design package submitted to Caltrans.

    Original evidence ↗

What happens next

Secure final design and right-of-way; then establish construction procurement

What remains uncertain

Evidence confirms the described municipal planning, funding or project status. Dates forecast by the City are not proof that future construction has commenced, and funding or approvals do not mean a facility is open.

Official maps, designs and site visuals

Original publisher links, not unlicensed photographs or invented project renderings.

Sources and documents

91% editorial confidence · Evidence assessment

Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.

Sources reviewed 30 October 2026.