Latest verified development
October 2026 owner construction reportBoston Parks confirms this greenway section has been closed for construction since March 2026 and describes October construction activity. Budget is $3.6 million; approximately December 2026 is the forecast reopening.
Project in numbers
About the project
Public-path and open-space upgrades; park route closed through construction including Gove Street crossing, with accessible detours.
Verified development history
- October 2026 owner construction report
Boston Parks confirms this greenway section has been closed for construction since March 2026 and describes October construction activity. Budget is $3.6 million; approximately December 2026 is the forecast reopening.
Original evidence ↗ - 2 November 2026 editorial review
City confirms physical site closure and continuing construction, with October owner bulletin.
Original evidence ↗
What happens next
The city's approximate December 2026 finish has not been certified, so Current remains appropriate.
What remains uncertain
Original owner documentation reviewed 2 November 2026; scheduled closures, projected completion and verified physical work are distinguished. Confidence indicates editorial support, not a calibrated delivery forecast.
Official maps, designs and site visuals
Original publisher links, not unlicensed photographs or invented project renderings.
Sources and documents
95% editorial confidence · Evidence assessment
Editorial confidence describes how well the cited records support this account. It is not a calibrated probability of project completion. Source event dates are distinct from research review dates.
Sources reviewed 2 November 2026.